Environmental Impact Statement Chapter 20.0 Cumulative impacts
Table of contents
Accessibility
This digital version of the EIS is designed to be accessible to all users, providing screen reader compatibility, keyboard navigation, and described images. If you require additional assistance or have specific accessibility needs, please contact us at lightrailtowoden@act.gov.au or call 1800 956 409.
20.0 Cumulative impacts
This chapter provides an assessment of the potential cumulative and facilitated impacts of the Project with other nearby developments.
20.1 Cumulative impacts defined
Cumulative impacts have the potential to occur when benefits or impacts from a project overlap or interact with those of other projects, potentially resulting in a larger overall impact (positive or negative) on the environment or local communities. Cumulative impacts may occur when projects are constructed or operated concurrently or consecutively.
The extent to which another development or activity could interact with the construction and/or operation of the Project would depend on the scale, location and/or timing of the development or activity. Generally, cumulative impacts would be expected to occur where other long-duration or large magnitude construction activities are undertaken close to, and over a similar timescale to, construction activities for the Project; or where consecutive construction occurs in the same area. Additionally, operation of the Project could cause cumulative benefits when the Project interacts with or possibly enhances the benefits of other Projects.
20.2 Assessment approach
The cumulative impact assessment methodology for the Project included:
- Identifying relevant developments that could be included in the cumulative impact assessment
- Applying screening criteria to determine which developments should be included in the cumulative impact assessment
- Assessing the potential cumulative impacts of the projects screened into the cumulative impact assessment, including identification of relevant issues likely to have material cumulative impacts during construction and/or operation of the Project (e.g. traffic, noise and vibration, landscape character and visual amenity, etc.)
- Identifying suitable mitigation measures to manage potential cumulative impacts.
The Cumulative Impact Assessment Guidelines for State Significant Projects (DPIE, 2022) has been adopted in the absence of Territory specific qualitative criteria.
A summary of the cumulative impact assessment methodology is shown on Figure 20-1.

20.2.1 Criteria for inclusion of potential projects
Potential projects identified for consideration in the cumulative impact assessment included those that met the following criteria for inclusion:
- Spatially relevant (i.e., where a development is considered to overlap with or occurs in close proximity to the Project)
- Timing (i.e., the expected timing of its construction and/or operation overlaps or occurs consecutively to construction and/or operation of the project)
- Scale (i.e., large-scale major development or infrastructure projects that have the potential to result in cumulative impacts with the Project, as listed on the Infrastructure Canberra (iCBR) and other ACT Government websites. Minor developments such as alterations to residential properties for example, were not included due to the nature and limited extent of those developments to interact cumulatively with the Project)
- Status (i.e., projects in development with sufficient publicly available information to inform this environmental impact statement and with an adequate level of detail to assess the potential cumulative impacts).
20.2.2 Projects included in, or excluded from the cumulative impact assessment
Projects identified and considered in the cumulative impact assessment are listed in Table 20-1. This table identifies construction and operational timeframes for each project (where known) considered in the cumulative impact assessment and how these overlap with the Project. Subject to planning approval and procurement, construction of the Project is anticipated to commence in 2029 and would take about four to five years to complete. The first passenger services are proposed to start in 2034.
The developments in Table 20-1 were identified as meeting the screening criteria at the time of the assessment. As noted in Section 20.2.1, projects have been screened out if insufficient project and environmental assessment information is publicly available.
Several large-scale infrastructure projects and developments within 1km of the Project area have been screened out from the cumulative impact assessment for the Project, primarily due to their planned timeframes for construction and operation. Developments anticipated to be in operation before the start of this Project's construction phase were excluded from further analysis because they would not overlap with the Project's construction timeline and thus would not generate cumulative construction impacts. Without concurrent construction periods, the potential for interaction between these projects and this Project would be minimised, removing the likelihood of compounded effects. As a result, these operational projects were not considered further in the cumulative impact assessment. Key projects screened out for these reasons include:
- National Security Office Precinct (Block 5 Section 1 Barton)
- Commonwealth Avenue Bridge Renewal Project
- CIT Woden Youth Foyer
- CIT Woden Education Campus
- Woden Interchange
- Southern Cross Club Build-to-Rent project.
These developments were assumed to be operational in relevant environmental assessments in Chapter 12 (Commonwealth Avenue precinct) to Chapter 19 (Mitchell Depot site), with traffic generated from their operations accommodated in the strategic traffic model.
As part of the revised, final Environmental Impact Statement (EIS), the cumulative impacts of the Project would be reassessed and would consider any new publicly available information that has been made available since the preparation of this assessment. Prior to the commencement of construction, proponents of other projects in the area would be identified and engaged with to understand potential cumulative impacts and coordinate mitigation and management (refer to mitigation measure CU1 in Section 20.7).
Project, status and indicative timing | Description of the project | Location relative to the Project | Precincts where cumulative impacts may occur |
---|---|---|---|
Acton Waterfront - future city neighbourhood Status: Currently in planning and development Timing: Unknown |
A masterplan is currently in development for a city neighbourhood connecting the city to the lake immediately adjacent to Ngamawari. This would be located on the area behind the park and feature a proposed mix of shops, businesses, cafes, recreational activities, and residential accommodation. This area would be located immediately west of the approved Light Rail Stage 2A (LRS2A) Commonwealth Park Stop. Planning and consultation for the proposed Acton Waterfront neighbourhood commenced in October 2022, with a concept masterplan developed in 2023. The creation of an estate development plan is currently underway (City Renewal Authority, 2024). The Acton Waterfront - future city neighbourhood differs from the Acton Waterfront Development 'Ngamawari' public park Stage 1A (interim works) and Stage 1B (permanent works), which are planned to complete construction prior to construction of this Project, and were therefore screened out of this assessment. |
Acton Waterfront, northern foreshore of Lake Burley Griffin, immediately west of the approved Commonwealth Park Stop |
Commonwealth Avenue |
Signage in the National Triangle Status: Unknown Timing: Unknown |
This project is planned by the National Capital Authority (NCA) and involves upgrading the existing red vehicular directional and interpretive signage to improve the aesthetic across the National Triangle. The new signage would incorporate the new National Triangle branding and update the content of the signage. While the scale of this project is relatively minor, it has been included due to its potential contribution to visual impacts in a highly visually sensitive area (the National Triangle). |
Throughout the National Triangle precinct |
National Triangle |
Canberra Brickworks Redevelopment Status: Development application submitted Timing: Construction expected to commence in 2025, however planned completion is unknown |
The Canberra Brickworks Redevelopment is planned to consist of parkland, residential, commercial and retail uses. The redevelopment would provide a maximum of 380 residential dwellings, including low density houses, terraces and apartment buildings, up to a maximum height of three storeys. |
Around 500 m north of the Project area on Yarra Glen near Cotter Road (Blocks 1,7 and 20 Section 102, Division of Yarralumla) |
Inner South Yarra Glen |
North Curtin Residential Area and Diplomatic Estate Status: Planning underway, with Amendment 95 to the National Capital Plan (to enable to the development) approved by the Minister Timing: Unknown |
The North Curtin Residential Area and Diplomatic Estate proposes 1,300 new dwellings, and seeks to accommodate the long-term growth in diplomatic missions in Australia's national capital. |
Immediately west of the Project area on Yarra Glen near Cotter Road (Block 4, Section 106 and Block 5, Section 121, Division of Curtin) |
Yarra Glen |
Matilda Street car park redevelopment Status: Currently in planning and development Timing: Construction expected to commence in 2026/2027 however planned completion is unknown |
The existing Matilda Street car park site is proposed for land release and future mixed use development. The planned redevelopment includes a mixed-use development with 200 dwellings. |
Immediately west of the Woden Interchange (Block 1, Section 7, Division of Phillip) |
Woden |
Hellenic Club redevelopment Status: Approval received Timing: Construction expected to commence in 2024, however planned completion is unknown |
The planned redevelopment includes mixed-use development including commercial, retail, entertainment, community and hotel uses at the existing site of the Hellenic Club. |
Immediately north-west of the Woden Interchange (Block 21, Section 6, Division of Phillip) |
Woden |
Woden Zone Substation to Canberra Hospital Underground High Voltage and Optical Fibre Connection Status: Currently in planning and development Timing: Unknown |
Installation of underground high voltage electrical and optical fibre communications infrastructure between Woden Zone Substation and Canberra Hospital to facilitate additional load at Canberra Hospital. The installation would be completed via trenching and under boring. |
Infrastructure would pass through the Project area from Theodore Street, passing through Melrose Drive, continuing through Yamba Drive to the east |
Woden |

20.3 Previous Light Rail network stages
The Project would extend the existing and planned Light Rail network in Canberra. Light Rail Stage 1 (LRS1) is currently operational. Based on current program information LRS2A is anticipated to begin operation prior to the start of main construction works of the Project.
Given that previous stages of the Light Rail network would be operational by the time the Project commences construction, and due to the linear nature of the Project, and previous stages, cumulative impacts are not predicted to occur. LRS1 and LRS2A have been considered throughout Part B (Environmental impact assessment) as part of the baseline environment for the Project (e.g. the existing environment in which this Project would be constructed).
Construction compounds A1 and A2 are currently used as construction compounds for the LRS2A project. Off-street parking losses associated with the use of these construction compounds for LRS2A would continue for the Project. However, there would be a gap between completion of construction of LRS2A and construction of the Project commencing where the construction compound is not in use.
Benefits of the extended Light Rail network (including this Project and the previous Light Rail network stages) are considered in Chapter 2 (Need for the Project).
20.4 Cumulative impacts - construction
Potential cumulative impacts during construction are related to:
- Traffic and transport
- Biodiversity
- Non-Aboriginal heritage
- Landscape character and visual amenity
- Air quality
- Socioeconomic
- Hydrology, flooding, and water quality
- Noise and vibration.
These impacts are summarised in the following sections. Further details on the potential cumulative impacts during construction are presented in the respective technical reports.
The timeline for construction of several of the identified surrounding developments is currently unknown. For the purposes of this construction cumulative assessment, it was conservatively assumed that all of these surrounding developments would be under construction at the same time as the Project.
20.4.1 Traffic and transport
The Project would involve temporary construction traffic arrangements and construction activity at the construction compounds and ancillary facilities along the alignment. The construction impact assessment presented in Technical Report 1 - Traffic and transport considers the cumulative impacts of various temporary traffic arrangements being implemented concurrently along the Project alignment and the additional construction traffic generated by the Project.
The following developments were identified as potentially resulting in cumulative traffic impacts with the Project during construction:
- Acton Waterfront - future city neighbourhood - construction traffic would likely use Commonwealth Avenue, a proposed construction haulage route for the Project
- Canberra Brickworks redevelopment - construction traffic would likely use Yarra Glen, which is a proposed construction haulage route for the Project
- North Curtin Residential Area and Diplomatic Estate - construction traffic would likely use Yarra Glen, Carruthers Rd and/or Cotter Rd, which is a proposed construction haulage route for the Project
- Hellenic Club redevelopment - construction traffic would likely use Launceston Street, Yamba Drive, and/or Melrose Drive, which are proposed construction haulage routes for the Project
- Matilda Street car park redevelopment - construction traffic would likely use Launceston Street, Yamba Drive, and/or Melrose Drive, which are proposed construction haulage routes for the Project. Construction of this site would result in a further reduction in available off-street public car parking within the Woden precinct.
Construction traffic volumes associated with these surrounding development projects are currently unknown. However, these projects would be spread across the extent of the study area for the traffic and transport assessment, and therefore, the construction traffic associated with each of these projects would be distributed across various haulage routes.
The proposed construction methodology for the Project would retain road network accessibility by maintaining traffic flow along key transport corridors during the construction works. Intersection and track crossing works would occur during weekend closures when traffic volumes on the surrounding road network are lower. Diversions would be available when block closures are implemented during the construction of the National Triangle-Barton alignment option.
While the proposed construction haulage routes for the Project have been identified to be the most direct to the construction compounds from the arterial road network, construction vehicles associated with the surrounding projects would likely use some of the same routes, resulting in a cumulative construction traffic impact on road network operations.
Most construction vehicle activity (travelling to and from site) during the Project's construction would occur outside of AM and PM peak road network periods. Considering the distance between the surrounding developments and the likely distribution of construction vehicle volumes on the surrounding road network, the cumulative construction traffic impact of these developments with the Project would represent only a small proportional increase in the total traffic volumes on the broader road network. This may result in a minor increase in vehicle delay and travel time on the surrounding road network.
As outlined in Chapter 21 (Environmental management and mitigation measures) and Appendix L (Environmental Management Plan outline), a Construction Traffic Management Plan (CTMP) would be prepared for the Project to provide details on proposed measures to minimise the cumulative traffic impact of construction works on surrounding road users. Chapter 21 (Environmental management and mitigation measures) also includes mitigation measures that would be applied to manage impacts to the transport network.
Measures which would contribute to management of cumulative traffic impacts could include:
- Scheduling of most deliveries outside of peak road network periods (including outside of standard construction hours where required to minimise impacts on the road network)
- Encouraging workers to use alternative transport arrangements, such as active and public transport or to car-pool, thereby minimising the number of single-person private vehicles generated by the works
- Use of shuttle buses to transport workers to/from the Project area and between construction compounds and work areas.
Construction environmental management is discussed further in Chapter 21 (Environmental management and mitigation measures).
20.4.2 Biodiversity
The Project area is positioned within a highly modified urban environment. While it does not support ecological communities listed under the Environment Protection and Biodiversity Conservation Act 1999 or Nature Conservation Act 2014, it does support habitat for a number of threatened species and contributes to connecting core habitat within the urban context.
A review of available information associated with the developments identified in Section 20.2.2 was carried out to determine the potential cumulative impacts on biodiversity-related Matters of National Environmental Significance (MNES) under the EPBC Act and protected species under the Territory's NC Act.
The North Curtin Residential Area and Diplomatic Estate had sufficient ecological information available to inform this assessment. The ecological assessment report for this project (Umwelt, 2022a) confirmed that this site supports patches of native vegetation, including native grasslands and amenity plantings, which provide habitat for woodland birds and Golden Sun Moth (Synemon plana) habitat. It is not known whether options to avoid or mitigate impacts on MNES and protected species from this project have been determined.
The Project area also supports Golden Sun Moth (Synemon plana) habitat that is contiguous with an adjacent site for the proposed National Security Office Precinct development (within the Barton precinct). These project examples demonstrate that current planned developments within the local landscape may contribute to a cumulative impact on the Golden Sun Moth and other species, which when combined with the impacts from this Project, may be significant.
20.4.3 Non-Aboriginal heritage
Cumulative heritage impacts have the potential to occur where developments near to the Project are constructed concurrently or consecutively. These are discussed in Table 20-2 and further detail can be found in Technical Report 3 - Heritage.
Precinct | Relevant projects | Assessment |
---|---|---|
Commonwealth Avenue |
|
The Acton Waterfront - future city neighbourhood would be expected to impact the heritage values of Lake Burley Griffin and Adjacent Lands from alterations to the significant generous, public spaces of its foreshores, and to the significant historical landscape of the Central National Area of Canberra more generally. It is likely that works for this project and the Project would be underway at the same time. At a landscape scale, it is likely that there would be cumulative impacts from both projects due to the separate but similar way in which they would have adverse impacts on the significant heritage values of their heritage context. |
Yarra Glen |
|
The scope of works and impacts from this project are yet to be further defined as it is in the early stages of strategic planning. It is possible that there may be associated impacts to the Project area with cumulative effects such as to the Royal Australian Mint on the other side of Adelaide Avenue. |
Further consideration of other permanent changes to the setting of heritage items as a result of other projects, including those which would be complete prior to the construction of this Project, can be found in Technical Report 3 - Heritage.
20.4.4 Landscape character and visual amenity
Cumulative landscape and visual impacts have the potential to occur where developments near to the Project are constructed concurrently or consecutively. Potential cumulative landscape and visual impacts during construction are discussed in Table 20-3.
Precinct | Relevant projects | Assessment |
---|---|---|
Commonwealth Avenue |
|
The Acton Waterfront has been subject to ongoing construction activity due to the lake reclamation, boardwalk extension and construction of Henry Rolland Park. Construction activity in the vicinity of this area is expected to continue during construction of the approved LRS2A. It is likely that the Project would be under construction at the same time as the Acton Waterfront - future city neighbourhood. The Project would prolong the occurrence of construction activity within the precinct near the Acton Waterfront, including construction compounds adjacent to Commonwealth Avenue (proposed as part of this Project). Further to this, the visible area of construction activity would extend from the existing land-based works to across Lake Burley Griffin, with visual receptors using the park and along the waterfront experiencing views to construction over a greater proportion of the surrounding landscape. This has the potential to be a substantial visual impact to sensitive visual receptors who may be using the existing park and waterfront for recreational purposes. If parts of the Acton Waterfront - future city neighbourhood are completed and occupied during the construction period of the Project, residential and commercial properties would potentially have views to the construction activity of the Project. This would be an ongoing visual impact during construction, although one that these visual receptors would have been aware of prior to taking up occupation of their properties, which may lessen their sensitivity to these anticipated temporary impacts. |
National Triangle |
|
If construction of this project were to occur simultaneously with the Project, there would be little to no increase in perceived construction activity if this project was located within the Project area. The replacement / upgrade of signage would also potentially be undertaken within the Project area, minimising the impact of these two projects where they are concurrent. |
Yarra Glen |
|
It is likely that the Project would be under construction at the same time as the Brickworks Precinct and the North Curtain Residential Area and Diplomatic Estate. Development of these sites may visually link construction activities, resulting in a substantial increase in the visible construction activity in the local area. This would comprise a substantial visual impact from surrounding roads, including Yarra Glen, Cotter Road, and from recreational visitors to Yarralumla Creek. It is unlikely that any residents would see all three projects under construction at once, however, would experience an overall increase in construction activity in the local area as they travelled to and from their homes. |
Woden precinct |
|
Construction of the Project would likely be experienced as an extension of construction activities related to other projects within the Woden area. The three identified projects would potentially have overlapping construction activities with the Project, reinforcing the visual character of an area under active development. |
20.4.5 Air quality
The adoption of mitigation measures set out in Chapter 21 (Environmental management and mitigation measures) and the construction management approach set out in Appendix L (Environmental Management Plan outline) are expected to result in the adequate management of dust and other emissions for the Project. The air quality risks associated with construction of infrastructure are well known and generally well managed using standard mitigation measures. Potential cumulative air quality impacts would be temporary and managed through consultation with the relevant stakeholders and coordinating construction activities with other nearby developments.
20.4.6 Socioeconomic
The construction of the Project has the potential to result in socioeconomic benefits associated with increased employment and training opportunities, particularly for construction workers. Should other identified projects be constructed concurrently, this benefit may be enhanced.
Potential cumulative socioeconomic impacts during construction may arise where these projects are constructed concurrently with the Project, and could include economic, health and wellbeing and traffic and access benefits and challenges.
Economic
The cumulative economic effects associated with the construction of Project, alongside other concurrent projects, could result in both benefits and challenges. If other projects are constructed concurrently with the Project, the cumulative impact could amplify the socioeconomic benefits associated with employment and training opportunities. The combined demand for construction workers, traffic professionals, planners, and related professions could create a broader pool of jobs across multiple sectors. This increased demand would particularly benefit local workers, as well as vulnerable communities, including Indigenous and disadvantaged groups, who may have targeted employment opportunities.This could lead to workers gaining experience from multiple large-scale projects resulting in a more skilled local workforce, and increase future employability in infrastructure development.
Increased employment for construction workers would likely lead to greater local expenditure, benefiting businesses and services in the surrounding areas. The influx of workers and the economic activity generated by large-scale projects could also stimulate further investments in the region, potentially leading to long-term economic growth.
Conversely, the increased demand for construction workers, engineers, planners, and other skilled professionals could reduce the availability of labour for other local community projects or services. This reduction in available labour could increase wages and competition for workers, which may lead to delays in project timelines or cost overruns. This could also limit resources available for other sectors. For example, essential services, housing developments, or smaller-scale municipal projects might struggle to attract labour, particularly in trades like residential construction, leading to delays or higher costs impacting housing affordability.
Health and wellbeing
Cumulative impacts related to the construction of the Project, particularly when combined with other nearby projects, may substantially affect the wellbeing of some residents and communities. Continuous construction activities can impact daily life through increased traffic, noise, reduced pedestrian accessibility, and a decline in local amenity. These disruptions can lead to frustration, stress, and even construction fatigue, which may have a detrimental effect on both mental and physical health. The Commonwealth Avenue and Woden precincts are especially vulnerable due to the extended timeline and scope of overlapping large-scale developments.
For individuals with mobility constraints, these impacts may be even more pronounced. Reduced pedestrian accessibility and construction-related obstacles could affect their ability to navigate through impacted areas, exacerbating feelings of isolation and stress. Addressing these concerns through coordinated construction activity and engagement with nearby projects would mitigate some of the potential negative effects experienced by vulnerable groups.
Traffic and access
As identified in Section 20.4.1, there is potential for cumulative construction traffic impacts, which may further impact access to social infrastructure, events, and attractors in the area, causing inconvenience for residents and visitors.
Concurrent construction projects, such as the Acton Waterfront development the Canberra Brickworks redevelopment and development projects in Woden, would likely share proposed construction haulage routes or generally lead to an increase in construction vehicles. This could exacerbate congestion, especially during peak hours, leading to delays that affect access to local amenities and social infrastructure. It is also important to recognise that these cumulative impacts may disproportionately affect individuals with mobility constraints. Increased delays and reduced accessibility to public spaces can significantly hinder their ability to navigate the community effectively.
20.4.7 Hydrology, flooding and water quality
Potential cumulative hydrology, flooding, and water quality impacts during construction are discussed in Table 20-4.
Predicted cumulative impacts of these developments and the Project would be similar in nature to those discussed in Section 11.5.1 such as changes to surface water quality (e.g. through run off from construction sites) or changes to flood characteristics. Hydrology, flooding, and water quality mitigation measures would be implemented (as outlined in Chapter 21 (Environmental management and mitigation measures)) which would appropriately manage these risks. Potential cumulative impacts would also be managed through consultation with the relevant stakeholders and coordinating construction activities with other nearby developments.
Precinct | Relevant projects | Assessment |
---|---|---|
Yarra Glen |
|
The North Curtin Residential Area and Diplomatic Estate lies within and adjacent to the Project area west of Yarra Glen and south of Cotter Road, and is adjacent to Yarralumla Creek. Due to its proximity to the light rail alignment and the size of its construction footprint, this development is likely to have an impact on the hydrology, flooding, and water quality of the receiving waterways during the construction phase, and there is a risk of spills or other forms of contamination. It has been conservatively assumed that construction of this project would occur concurrently with the Project. The potential for cumulative impacts to occur would be appropriately mitigated through standard environmental controls to manage erosion and sedimentation, and risk of spills (refer further to Chapter 21 (Environmental management and mitigation measures)). |
Woden |
|
The site of the Hellenic Club lies directly west of the light rail alignment. The proposed Matilda Street car park redevelopment is located between Matilda Street, Bowes Street, and Callam Street in the Woden town centre. For both of these developments, the existing sites are largely impervious, and as such, there would be little change to the ratio of pervious and impervious surfaces, and therefore no material change in drainage and flooding characteristics from the existing conditions. However, as the development sites are close to both the light rail alignment and Yarralumla Creek, the potential for spills and uncontrolled runoff from construction activities may be exacerbated. The potential for cumulative impacts to occur would be appropriately mitigated through standard environmental controls to manage erosion and sedimentation, and risk of spills (refer further to Chapter 21 (Environmental management and mitigation measures)). |
20.4.8 Noise and vibration
The following developments have been identified as potentially having cumulative construction noise and vibration impacts with the Project:
- Acton Waterfront - future city neighbourhood
- Canberra Brickworks redevelopment
- North Curtin Residential Area and Diplomatic Estate
- Hellenic Club redevelopment
- Matilda Street car park redevelopment
- Woden Zone Substation to Canberra Hospital Underground High Voltage and Optical Fibre Connection.
These developments are located at varying distances from the Project and may have an impact on the construction noise levels experienced at noise sensitive receivers depending on the construction activities occurring simultaneously and the distance from the Project. If another construction activity outside of the Project was occurring at a similar noise level to the Project construction activities, the resulting construction noise level may be 3 dB higher than the construction noise levels presented in the construction assessment for the Project (refer to Section 5 of Technical Report 9 - Noise and vibration). Similarly if two construction activities outside of the Project were occurring at a similar noise level to the Project construction activities, the resulting construction noise level may be 5 dB higher than the construction noise levels presented in the construction assessment for the Project (refer to Section 5 of Technical Report 9 - Noise and vibration).
In accordance with measures identified to manage cumulative construction impacts (refer to Section 20.7), proponents of other developments in the area would be consulted with during construction to confirm the potential for overlapping impacts and coordinate impact mitigation and management (for example, respite periods), where relevant.
20.5 Cumulative impacts - operation
Potential cumulative impacts during operations are related to:
- Traffic and transport
- Non-Aboriginal heritage
- Landscape character and visual amenity
- Hydrology, flooding and water quality
- Noise and vibration.
These impacts are summarised in the following sections. Further details on the potential cumulative impacts during operations are presented in the respective technical reports.
The timeline for the completion and operation of several of the identified surrounding developments is currently unknown. For the purposes of this operational cumulative assessment, it was conservatively assumed that all of the identified nearby developments would be completed and operational at the same time as the Project.
20.5.1 Traffic and transport
Most of the identified surrounding developments (in Section 20.4.1) would likely generate additional traffic once operational. Operational traffic associated with these future developments were considered in the Zenith Strategic Transport Model which informed the traffic and transport assessments. Therefore, the cumulative impact of these developments with the Project has already been considered in the traffic modelling and impact assessment presented in Technical Report 1 - Traffic and transport.
The Project would provide a relatively direct, alternative route for transport from these surrounding developments to other locations along the alignment and connections to other regional public transport services. As such, the Project has the opportunity to reduce the traffic generation of these surrounding developments by providing an alternative accessible mode of transport. The active travel infrastructure being delivered as part of the Project also has the potential to create a mode shift away from private vehicle travel increasing walking and cycling travel.
20.5.2 Non-Aboriginal heritage
Potential cumulative non-Aboriginal heritage impacts during operation of the Project are discussed in Table 20-5. Further detail can be found in Technical Report 3 - Heritage.
Precinct | Relevant projects | Assessment |
---|---|---|
Commonwealth Avenue |
|
Once operational, the Project would comprise a continuation of light rail along Commonwealth Avenue extending south from the approved Commonwealth Park Stop. At a landscape scale, it is likely that there would be cumulative impacts from both projects due to the separate but similar way in which they would have adverse impacts on the significant heritage values of their heritage context. |
Yarra Glen |
|
The scope of works and impacts from this project are yet to be further defined as it is in the early stages of strategic planning. It is possible that there may be associated impacts to the Project area with cumulative effects such as to the Royal Australian Mint on the other side of Adelaide Avenue. |
Further consideration of other permanent changes to the setting of heritage items as a result of other projects, including those which would be complete prior to the operation of this Project, can be found in Technical Report 3 - Heritage.
20.5.3 Landscape character and visual amenity
Potential cumulative landscape and visual impacts during operation are discussed in Table 20-6.
During operation, cumulative landscape and visual impacts of the Project and other developments would be limited. The Project and developments discussed in Table 20-6 would be designed to integrate into the landscape, noting the importance of the Canberra city layout. These projects are each consistent with the continued visual nature of Canberra as a city and urbanised environment.
Precinct | Relevant projects | Assessment |
---|---|---|
Commonwealth Avenue |
|
Once operational, the Project would comprise a continuation of light rail along Commonwealth Avenue extending south from the approved Commonwealth Park light rail stop. The Project would complement this development by providing public transport accessibility to the planned neighbourhood, which would be designed with consideration of the approved light rail stop at Commonwealth Park. The Project would be visually recessive and positioned within an existing transport corridor, and would not comprise a substantial increase in impact when considered cumulatively. As such the two projects would be visually complementary and would not result in adverse visual impacts. |
National Triangle |
|
Given that the Signage in the National Triangle project would generally involve replacement/upgrade of existing signage with signage of a similar scale, there would be no additional cumulative visual or landscape impact with this Project, once operational. |
Yarra Glen |
|
During operation of the Project, the North Curtin Residential Area and Diplomatic Estate would be likely to physically join the Canberra Brickworks redevelopment to the Project. There would be a substantial change in the landscape character of the land to the north / north-west of Yarra Glen, with the existing green open space shifting to residential and mixed-use development. The Project would not contribute substantially to this change in overall character shift of the area due to the relative low visual prominence of the Project in comparison to the large scale construction of residential and diplomatic built form. |
Woden precinct |
|
During operation of the Project, the Woden precinct would be substantially developed, however, exhibiting the commercial and residential town centre landscape character that already exists in the area. The Project and the identified developments would be visually consistent with this character, and are therefore not anticipated to result in adverse cumulative visual and landscape character impacts. |
20.5.4 Hydrology, flooding and water quality
Potential cumulative hydrology, flooding and water quality impacts during operation are discussed in Table 20-7. Land use changes associated with planned development, where known, were included in the baseline flood models used to inform the assessment carried out for the Project. This has allowed for an assessment of impacts that considers developments which may not be existing currently but are likely to be present once the Project is operational. A complete list of these developments is included in Technical Report 4 - Hydrology, flooding and water quality.
Precinct | Relevant projects | Assessment |
---|---|---|
Yarra Glen |
|
At present, this area consists of pervious grassland, and the replacement of this with concrete, asphalt, and other impervious materials has the potential to contribute materially to overland flows and stormwater flows. These estimated land use changes were included in the baseline flood model for Yarralumla Creek (described further in Technical Report 4 - Hydrology, flooding and water quality). The replacement of the existing grassland and natural surfaces with a development is likely to lead to increases in some pollutants and hydrocarbons within the receiving waterways. The addition of buildings and other infrastructure such as retaining walls may also divert or obstruct existing overland flow paths. Localised ponding may also be worsened, and the existing drainage network may reach capacity sooner or in locations where it had not previously. During operation, the Project would affect the receiving waterways through additional pollutant loads generated by new impervious areas, and potentially negatively affect localised flood depths if not mitigated effectively through improved drainage and landscape design. Mitigation measures are proposed in Chapter 21 (Environmental management and mitigation measures) to manage this impact. |
Woden |
|
While the Hellenic Club and Matilda Street car park redevelopments are unlikely to result in a major change of the ratio of pervious to impervious area, the addition of new buildings and infrastructure in this highly urbanised environment has the potential to negatively impact the peak flow and flood levels through the obstruction and diversion of existing overland flow paths. Localised ponding may also be worsened, and the existing drainage network may reach capacity sooner or in locations where it had not previously. During the operation of the Project, potential cumulative impacts of these developments with the Project could include increasing localised flooding due to new buildings and structures obstructing or diverting flow paths, or increased flood depths due to additional impervious areas. Mitigation measures are proposed in Chapter 21 (Environmental management and mitigation measures) to manage these potential impacts. |
20.5.5 Noise and vibration
No other light or heavy rail projects are currently proposed to be constructed in proximity of the Project area. Therefore, cumulative noise from operational rail activities is unlikely to impact noise sensitive receivers within the Project area.
The noise and vibration assessment of the Project in Technical Report 9 - Noise and vibration has also considered approved unbuilt developments that contain noise sensitive receivers as part of the baseline environment. This has allowed for an assessment of impacts to receivers which may not be existing currently but are likely to be present once the Project is operational. A complete list of these developments is included in Technical Report 9 - Noise and vibration.
20.6 Facilitated impacts
Facilitated impacts are consequences of actions taken by third parties, where the third-party action is facilitated to a major extent by the primary action, and the impacts of the third-party action could be reasonably foreseen. While there are developments located adjacent to the Project which would likely benefit from the extension of light rail from Commonwealth Park to Woden, these are not directly related and could occur regardless. Consideration of the cumulative impacts of these developments are detailed in Section 20.4 and Section 20.5. While these developments may give rise to environmental impacts, they would be subject to separate environmental assessment and approval activities.
20.7 Management and mitigation measures
Environmental management for this Project is detailed in Chapter 21 (Environmental management and mitigation measures). This includes construction and operational measures to manage cumulative impacts, that are applicable to the Project as a whole.
Management and mitigation measures have been proposed to reduce the potential cumulative impacts of the Project and other developments, which are identified in Table 20-8.
ID | Objective | Management and mitigation measure | Timing | Relevant precinct(s) |
---|---|---|---|---|
CU1 |
Managing cumulative impacts |
During design development and construction phases, consultation will occur with proponents of other projects in the area to:
|
Design and construction |
All |