Weekend work schedule
Scan & Plan - each week you can find out the latest dates for weekend work near you.
Night work takes place up to 10 nights per month in various locations along the freeway. Generally, night work takes place in locations where limited construction work can take place during the day when all freeway traffic lanes are open and being used by vehicle traffic.
Weekend work takes place from Friday night to Monday morning, and on long weekends from Thursday or Friday night to Monday or Tuesday morning. Over the weekends, we make productive use of lower traffic volumes in Sydney to set up road closures and complete as much work as we can over the weekend, expediting the overall project work schedule.
Upcoming day and night work on Miller Street and Rosalind Street, Cammeray
Miller Street between Amherst Street and Ernest Street and at the Miller Street southbound on ramp, Cammeray:
In November 2025, we will be connecting underground Intelligent Transport Services (ITS) from a power source on Miller Street to electronic signage on the Warringah Freeway.
This work will be completed over several shifts of day and night work, including over two weekends. You will also see us working in multiple locations, including Miller Street between Ernest Street and Amherst Street, Miller Street bridge and at the Miller Street southbound on ramp.
We will be carrying out weekend work in the Northern precinct on the following dates:
10pm Friday 14 November to 6pm Sunday 16 November 2025
10pm Friday 28 November to 6pm Sunday 30 November 2025
For more information about the November 2025 weekend work please click here to view the 'November 2025 upcoming day and night work on Miller Street and Rosalind Street, Cammeray' community notification (MW409N)'.
Work locations
Temporary weekend and daytime pedestrian access changes
November 2025 - Weekend work activities
November weekend traffic changes in Cammeray and Neutral Bay
Upcoming weekend work and temporary traffic changes, North Sydney & Neutral Bay
Between Milsons Point and Ernest Street, North Sydney:
In February 2026, we will be continuing consecutive weekend day and night work along the freeway and intersections in North Sydney and Neutral Bay, to speed up the work programme and reduce our overall impact to the surrounding community.
We will be carrying out weekend work in the southern precinct on the following dates:
10pm Friday 6 February to 5am Monday 9 February 2026
For more information about the February 2026 weekend work please click here to view the 'February 2026 upcoming weekend work and temporary traffic changes, North Sydney & Neutral Bay' community notification (MW435S)'.
February 2026 - Weekend work activities
February 2026 - Weekend work map
February 2026 - Weekend work traffic changes
February 2026 - South work areas and work activities
| Location | Work activities | Closure Times |
|---|---|---|
| Warringah Freeway northbound lanes, between Lavender Street and Falcon Street | Excavating, hammering, asphalting, pavement construction work, installing concrete, linemarking, installing and removing barriers, sawcutting, installing signage, installing Intelligent Transport Systems (ITS), installing drainage and utility services, backfilling and compacting. |
10pm Friday 6
February to 5am
Monday 9 February
2026 |
| Arthur Street, North Sydney | New pavement installation, installing concrete, excavating, hammering, drainage work, Intelligent Transport Systems (ITS) work, sawcutting, backfilling, compacting and temporary parking removal |
10pm Friday 6
February to 5am
Monday 9 February
2026 |
| Warringah Freeway southbound lanes, between Falcon Street and Mount Street | Excavating, hammering, asphalting, pavement construction work, installing concrete, linemarking, sawcutting, installing and removing barriers, installing signage, installing Intelligent Transport Systems (ITS), installing drainage and utility services, backfilling and compacting |
10pm Friday 6
February to 5am
Monday 9 February
2026 |
| Miller Street and Falcon Street intersection | Excavating, hammering, asphalting, pavement construction work, installing concrete, linemarking, sawcutting, installing and removing barriers, installing signage, installing Intelligent Transport Systems (ITS), installing drainage and utility services, backfilling and compacting and temporary parking removal |
10pm Friday 6
February to 5am
Monday 9 February
2026 |
| Mount Street western on ramp and Warringah Freeway southbound lanes | Excavating, hammering, asphalting, pavement construction work, installing concrete, linemarking, sawcutting, installing and removing barriers, installing signage, installing Intelligent Transport Systems (ITS), installing drainage and utility services, backfilling and compacting |
10pm Friday
6 February to
5am Monday 9
February 2026 10pm Friday 27 February to 6am Sunday 1 March 2026 (low noise work on Saturday 28 February 2026 night) |
| Warringah Freeway southbound lanes between Berry Street and Mount Street | Excavating, hammering, asphalting, pavement construction work, installing concrete, linemarking, sawcutting, installing and removing barriers, installing signage, installing Intelligent Transport Systems (ITS), installing drainage and utility services, backfilling and compacting |
10pm Friday
6 February to
5am Monday 9
February 2026 |
February 2026 - South temporary traffic changes
| Location | Closure Times |
|---|---|
| Falcon Street northbound bus only off ramp closed |
9pm Friday 6 February to 5am Monday 9
February |
| Berry Street northbound on ramp closed | 10pm Friday 6 February to 6am Saturday 7 February 10pm Saturday 7 February to 6am Sunday 8 February 10pm Sunday 8 February to 5am Monday 9 February |
| Mount Street western on ramp closed | 10pm Friday 27 February to 6am Sunday 1
March 2026 |
| Pacific Highway to Arthur Street slip lane and Arthur Street closed | 9pm Friday 6 February to 5am Monday 9
February |
| Falcon Street southbound on ramp closed | 10pm Friday 6 February to 6am Saturday
7 February 10pm Saturday 7 February to 6am Sunday 8 February 10pm Sunday 8 February to 5am Monday 9 February |
| Arthur Street northbound slip lane closed | 9pm Friday 6 February to 5am Monday
9 February
|
| Sydney Harbour Tunnel northbound closed | 11pm Friday 6 February to 6am Saturday
7 February 11pm Saturday 7 February to 6am Sunday 8 February 10:30pm Sunday 8 February to 5am Monday 9 February |
| Sydney Harbour Tunnel southbound closed | 10pm Friday 6 February to 6am Saturday
7 February 10pm Saturday 7 February to 6am Sunday 8 February 10pm Sunday 8 February to 6am Monday 9 February |
| Alfred Street North road closed from Kurraba Road to Mount Street | Closed until early 2026 |
| Mount Street to Alfred Street North | Closed until early 2026 |
For more detailed work information, please view the 'Work activities map' and select the relevant work area using the bar on the left of the page.
Find out more about why we work over weekends in our weekend work fact sheet here.
*Please note, work dates are subject to change due to wet weather or other unforeseen events. As soon as new information becomes available, we will update the above information so it's important to check back each week for updates.