Weekend work schedule
Scan & Plan - each week you can find out the latest dates for weekend work near you.
Night work takes place up to 10 nights per month in various locations along the freeway. Generally, night work takes place in locations where limited construction work can take place during the day when all freeway traffic lanes are open and being used by vehicle traffic.
Weekend work takes place from Friday night to Monday morning, and on long weekends from Thursday or Friday night to Monday or Tuesday morning. Over the weekends, we make productive use of lower traffic volumes in Sydney to set up road closures and complete as much work as we can over the weekend, expediting the overall project work schedule.
Upcoming day and night work on Miller Street and Rosalind Street, Cammeray
Miller Street between Amherst Street and Ernest Street and at the Miller Street southbound on ramp, Cammeray:
In November 2025, we will be connecting underground Intelligent Transport Services (ITS) from a power source on Miller Street to electronic signage on the Warringah Freeway.
This work will be completed over several shifts of day and night work, including over two weekends. You will also see us working in multiple locations, including Miller Street between Ernest Street and Amherst Street, Miller Street bridge and at the Miller Street southbound on ramp.
We will be carrying out weekend work in the Northern precinct on the following dates:
10pm Friday 14 November to 6pm Sunday 16 November 2025
10pm Friday 28 November to 6pm Sunday 30 November 2025
For more information about the November 2025 weekend work please click here to view the 'November 2025 upcoming day and night work on Miller Street and Rosalind Street, Cammeray' community notification (MW409N)'.
Work locations
Temporary weekend and daytime pedestrian access changes
November 2025 - Weekend work activities
November weekend traffic changes in Cammeray and Neutral Bay
Upcoming weekend work and temporary traffic changes, North Sydney & Neutral Bay
Between Milsons Point and Ernest Street, North Sydney:
In November 2025, we will be continuing consecutive weekend day and night work along the freeway and intersections in North Sydney and Neutral Bay, to speed up the work programme and reduce our overall impact to the surrounding community.
We will be carrying out weekend work in the southern precinct on the following dates:
10pm Friday 14 November to 6pm Sunday 16 November 2025
10pm Friday 28 November to 6pm Sunday 30 November 2025
For more information about the November 2025 weekend work please click here to view the 'November 2025 upcoming weekend work and temporary traffic changes, North Sydney & Neutral Bay' community notification (MW408S)'.
November 2025 - Weekend work activities
November 2025 - Weekend work map
November 2025 - Weekend work traffic changes
November 2025 - South work areas and work activities
| Location | Work activities | Closure Times |
|---|---|---|
| Miller Street and Falcon Street intersection | Concrete installation, pavement construction, barrier installation, sawcutting, hammering, excavating, asphalting, linemarking, overnight temporary parking removal, backfilling and compacting. |
10pm Friday 28 November to 6pm Sunday 30 November |
| Warringah Freeway northbound lanes, between High Street and Ernest Street | Excavating, hammering, asphalting, drilling, pavement construction, linemarking, realigning and installing barriers, sawcutting, installing signage, installing drainage and services, gantry work, installing safety screens, backfilling and compacting |
10pm Friday 14 November to 6pm
Sunday 16 November |
| Warringah Freeway southbound lanes, between Falcon Street and Mount Street | Excavating, hammering, asphalting, drilling, pavement construction, linemarking, sawcutting, installing Intelligent Transport Systems (ITS), installing drainage and services, installing streetlighting, backfilling and compacting |
10pm Friday 14 November to 6pm
Sunday 16 November |
| Mount Street bridge, Mount Street retaining walls and underpass, and Mount Street eastern ramp, and Warringah Freeway southbound lanes between Mount Street and High Street | Pavement work, excavating, hammering, installing concrete, asphalting, sawcutting, drilling, installing Intelligent Transport Systems (ITS), installing streetlights, installing drainage and services, gantry work, installing safety screens, retaining wall finishing work, backfilling and compacting |
10pm Friday 14 November to 6pm
Sunday 16 November |
| Alfred Street North retaining walls | Excavating, installing concrete, sawcutting, retaining wall finishing work, backfilling and compacting |
10pm Friday 14 November to 6pm
Sunday 16 November |
| Warringah Freeway southbound lanes, between High Street and Mount Street | Pavement work, excavating, installing concrete, installing barriers, sawcutting, backfilling and compacting |
10pm Friday 14 November to 6pm
Sunday 16 November | High Street and Arthur Street intersection | Removing and reinstating road pavement, relocating barriers, installing signage and street lighting, trenching, installing drainage and services, concreting, excavating, hammering, drilling, sawcutting, backfilling and compacting, asphalting and linemarking |
10pm Friday 28 November to
6pm Sunday 30 November |
>
November 2025 - South temporary traffic changes
| Location | Closure Times |
|---|---|
| Military Road northbound off ramp and Falcon Street northbound bus only off ramp closed |
10pm Friday 14 November to 6am Saturday
15 November 10pm Saturday 15 November to 7am Sunday 16 November November 10pm Sunday 16 November to 5am Monday 17 November (contingency) |
| Full northbound closure to Gore Hill Freeway | 12:30am Saturday 15 November to 6am
Saturday 15 November 1am Sunday 16 November to 7am Sunday 16 November 11pm Sunday 16 November to 5am Monday 17 November (contingency) |
| Berry Street northbound on ramp closed | 10pm Friday 14 November to 6am Saturday
15 November 10pm Saturday 15 November to 7am Sunday 16 November 10pm Sunday 16 November to 5am Monday 17 November (contingency) |
| Mount Street eastern on ramp closed | 9:30pm Friday 14 November to 6pm
Saturday 15 November 2025 |
| Cahill Expressway (lane 8) closed | 9:30pm Friday 14 November to 6pm
Saturday 15 November 2025
|
| Reversible lane closed | 8pm Friday 14 November to 5am Monday
17 November
|
| Sydney Harbour Tunnel northbound closed | 11pm Friday 14 November to 6am
Saturday 15 November 12:30pm Saturday 15 November to 7am Sunday 16 November 11pm Sunday 16 November to 5am Monday 17 November (contingency) |
| Pacific Highway to Arthur Street slip lane
closed *Access to Meriton maintained |
10pm Friday 28 November to 6pm Sunday
30 November 2025 |
| Arthur Street northbound slip lane *Access to Meriton maintained |
10pm Friday 28 November to 6pm Sunday
30 November 2025 |
| Alfred Street North road closed from Kurraba Road to Mount Street | Closed until early 2026 |
| Mount Street to Alfred Street North | Closed until early 2026 |
For more detailed work information, please view the 'Work activities map' and select the relevant work area using the bar on the left of the page.
Find out more about why we work over weekends in our weekend work fact sheet here.
*Please note, work dates are subject to change due to wet weather or other unforeseen events. As soon as new information becomes available, we will update the above information so it's important to check back each week for updates.