Weekend work schedule
Scan & Plan - each week you can find out the latest dates for weekend work near you.
Night work takes place up to 10 nights per month in various locations along the freeway. Generally, night work takes place in locations where limited construction work can take place during the day when all freeway traffic lanes are open and being used by vehicle traffic.
Weekend work takes place from Friday night to Monday morning, and on long weekends from Thursday or Friday night to Monday or Tuesday morning. Over the weekends, we make productive use of lower traffic volumes in Sydney to set up road closures and complete as much work as we can over the weekend, expediting the overall project work schedule.
Upcoming weekend work and temporary traffic changes, Cammeray & Neutral Bay
Between Ridge Street, North Sydney and Miller Street, Cammeray:
In August 2025, we will be carrying out day and night work over one weekend on the Warringah Freeway, Falcon Street shared user bridge and the Miller Street southbound on ramp, Cammeray. This will speed up the work program and reduce overall impact to the surrounding community. We will be carrying out weekend work in the Northern precinct on the following dates:
10pm Friday 15 August to 4:30am Monday 18 August 2025
For more information about the August 2025 weekend work for the project's northern precinct, please click here to view the 'Upcoming weekend work and temporary traffic changes, Cammeray & Neutral Bay' community notification (MW386N)
Work locations
Pedestrian impacts during Falcon Street shared user bridge ramp work activities
Pedestrian impacts during Miller Street southbound on ramp work activities
August 2025 - Weekend work activities
August weekend traffic changes in Cammeray and Neutral Bay
Upcoming weekend work and temporary traffic changes, North Sydney & Neutral Bay
Between Pitt Street and Falcon Street, North Sydney:
September 2025 - Weekend work activities
September 2025 - Weekend work map
5-7 September 2025 - Weekend work traffic changes
12-15 September 2025 - Weekend work traffic changes
19-22 September 2025 - Weekend work traffic changes
In September 2025, we will be continuing consecutive weekend day and night work along the freeway and intersections in North Sydney and Neutral Bay, to speed up the work programme and reduce our overall impact to the surrounding community.
We will be carrying out weekend work in the southern precinct on the following dates:
10pm Friday 5 September to 6pm Sunday 7 September 2025
10pm Friday 12 September to 5am Monday 15 September 2025
9:30pm Friday 19 September to 5am Monday 22 September 2025
9:30pm Saturday 27 September to 5am Monday 29 September 2025
For more information about the September 2025 weekend work please click here to view the 'September 2025 upcoming weekend work and temporary traffic changes, North Sydney & Neutral Bay' community notification (MW401S)'.
September 2025 South work areas and work activities
Location | Work activities | Closure Times |
---|---|---|
High Street and Arthur Street intersection | Pavement removal and installation work, trenching, drainage installation, concrete installation, asphalt installation, linemarking installation, excavating, hammering, sawcutting, surveying, backfilling and compacting |
10pm Friday 5 September to 6pm Sunday 7 September 2025 10pm Friday 12 September to 6pm Sunday 14 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 |
New Mount Street bus on ramp and Mount Street underpass | Pavement work, sawcutting, excavating, concrete installation work, barrier installation work, asphalting, rectification work, surveying, retaining wall work, backfilling and compacting |
10pm Friday 5 September to 6pm Sunday 7 September 2025 10pm Friday 12 September to 6pm Sunday 14 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 |
Berry Street on ramp and Warringah Freeway northbound lanes | Pavement installation, excavating, hammering, sawcutting, concrete installation, asphalt installation, barrier installation, landscaping, drainage and Intelligent Transport Systems (ITS) installation, steelfixing, backfilling and compacting |
10pm Friday 5 September to 6pm Sunday 7 September 2025 10pm Friday 12 September to 6pm Sunday 14 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 |
Warringah Freeway northbound and reversible lanes, between Mount Street and Falcon Street | Pavement installation, concrete installation, drainage installation, ITS installation, barrier installation, excavating, hammering, linemarking, asphalting, backfilling and compacting |
10pm Friday 5 September to 6pm Sunday 7 September 2025 10pm Friday 12 September to 6pm Sunday 14 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 |
Warringah Freeway southbound lanes, between Mount Street and Falcon Street | Pavement installation, concrete installation, drainage installation, ITS installation, barrier installation, excavating, hammering, sawcutting, drilling, linemarking, asphalting, backfilling and compacting |
10pm Friday 5 September to 6pm Sunday 7 September 2025 10pm Friday 12 September to 6pm Sunday 14 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 |
Miller Street and Falcon Street intersection | Utility installation work, concrete installation, pavement installation, asphalting, barrier installation, excavating, hammering, sawcutting, linemarking, backfilling and compacting | 10pm Friday 12 September to 5am Monday 15 September 2025 | High Street bridge | Excavating, existing footpath demolition, removal of contaminated materials, concrete installation work, backfilling and compacting | 10pm Friday 12 September to 6pm Sunday 14 September 2025 | Warringah Freeway northbound lanes between Fitzroy Street and Mount Street, and Pacific Highway | Pavement installation, concrete installation, drainage installation, ITS installation, barrier installation, excavating, hammering, sawcutting, drilling, linemarking, asphalting, backfilling and compacting |
10pm Friday 12 September to 5am Monday 15 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 | Warringah Freeway northbound and southbound lanes, between Burton Street and Pitt Street | Gantry modification work, scaffold installation, junction box installation, cabling, and signage testing work |
10pm Friday 5 September to 6pm Sunday 7 September 2025 9:30pm Saturday 27 September to 5am Monday 29 September 2025 | Existing Mount Street bus on ramp and Warringah Freeway outer lanes | Pavement construction work, sawcutting, excavating, hammering, concrete installation, asphalting, backfilling and compacting |
10pm Friday 5 September to 6pm Sunday 7 September 2025 10pm Friday 12 September to 6pm Sunday 14 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 | Alfred Street North between Mount Street and Whaling Road | Pavement work, sawcutting, excavating, hammering, concrete installation, asphalt removal and installation, kerb installation, barrier installation, median installation, surveying, rectification work, backfilling and compacting |
10pm Friday 5 September to 6pm Sunday 7 September 2025 10pm Friday 12 September to 5am Monday 15 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 | Alfred Street North, between Ridge Street and Winter Avenue | Crane set up and demobilisation, delivery or structures and materials, and edge protection installation | 10pm Friday 12 September to 6pm Sunday 14 September 2025 | >
September 2025 South temporary traffic changes
Location | Closure Times |
---|---|
Military Road northbound off ramp closed |
10pm Friday 5 September to 6am Saturday 6 September 2025 10pm Saturday 6 September to 6am Sunday 7 September 2025 10pm Friday 12 September to 6am Saturday 13 September 2025 10pm Saturday 13 September to 6am Sunday 14 September 2025 10pm Friday 19 September to 6am Saturday 20 September 2025 10pm Saturday 20 September to 6am Sunday 21 September 2025 10pm Sunday 21 September to 5am Monday 22 September 2025 |
Berry Street northbound on ramp closed | 9pm Friday 5 September to 5am Monday 8 September 2025 10pm Friday 12 September to 6am Saturday 13 September 2025 10pm Saturday 13 September to 6am Sunday 14 September 2025 10pm Friday 19 September to 5am Saturday 22 September 2025 |
Pacific Highway to Arthur Street slip lane closed *Access to Meriton maintained |
10pm Friday 5 September to 6pm Sunday 7 September 2025 |
Arthur Street northbound slip lane closed *Access to Meriton maintained |
10pm Friday 5 September to 6pm Sunday 7 September 2025 10pm Friday 12 September to 6pm Sunday 14 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 |
Right turn access from High Street westbound onto Arthur Street *Access to Meriton maintained |
10pm Friday 12 September to 6pm Sunday 14 September 2025 10pm Friday 19 September to 5am Monday 22 September 2025 |
Mount Street eastern on ramp closed | 9:30pm Friday 19 September to 6pm Sunday 21 September |
Reversible lanes closed |
10pm Friday 5 September to 6am Sunday 7 September 2025 10pm Friday 12 September to 3pm Sunday 14 September 2025 |
Falcon Street southbound on ramp closed | 10pm Friday 19 September to 6am Saturday 20 September 2025 10pm Friday 19 September to 6am Saturday 20 September 2025 10pm Friday 19 September to 6am Saturday 20 September 2025 |
Long-term road closures
Location | Closure Times |
---|---|
Alfred Street North closed between Kurraba Road and Mount Street closed | Closed until late 2025 |
Mount Street to Alfred Street North closed | Closed until late 2025 |
For more detailed work information, please view the 'Work activities map' and select the relevant work area using the bar on the left of the page.
Find out more about why we work over weekends in our weekend work fact sheet here.
*Please note, work dates are subject to change due to wet weather or other unforeseen events. As soon as new information becomes available, we will update the above information so it's important to check back each week for updates.