Click to view more information about night work for:
Temporary changes to motorist, cyclist and pedestrian may be in place. Always travel with care and follow the instructions of signage and traffic control.
Register for updates
Sign up to receive relevant notifications, construction updates and information right to your email.
31 October 2024
Our roadwork activities in November include switching the lanes of traffic on President Avenue between Princes Highway and West Botany Street – eastbound lanes will be moved to the southern side of President Avenue and a work zone will be established on the northern side. This change will enable the commencement of traffic management works and the installation of equipment, signage and signalling for the M6 Stage 1.
Stormwater drainage upgrades are near completion. Pavement and footpath works continue, including a slip lane from Princes Highway to President Avenue and works within the C6 compound (formerly 7-Eleven).
Three base slab pours within the tunnel portal are scheduled for this month, and we will be installing the precast deck on President Avenue bridge.
Read our November 2024 notification for the full program of roadworks construction activities.
28 October 2024
Site establishment activities in Whiteoak Reserve will commence on Tuesday 29 October, marking a milestone for the M6 Stage 1. Establishment activities will pave the way for the team to begin construction of the 5km shared pedestrian and cyclist pathway from Whiteoak Reserve to the existing site in Muddy Creek, adjacent to C.A. Redmond Field and Rockdale Women Sportsfield. Once complete, Whiteoak Reserve will be the northernmost point of the alignment, which will meander south through Bicentennial Park, across President Avenue via the new shared pathway bridge, before heading to Chuter Avenue via Scarborough Park north.
Our team will place site fencing along the project’s boundary in Whiteoak Reserve before site establishment activities begin. Learn more about site establishment by reading our latest notification for Whiteoak Reserve. Keep up to date with all ongoing construction by subscribing to our email distribution list.
24 October 2024
Tunnelling and construction work continues during November at Arncliffe. The electrical team has commenced the mainline fit-out, which includes installing mainline cable containment and essential devices. These installations will enable the operation of all electrical systems, including GPS and variable signage, for the tunnels when they are operational.
To learn more, view our latest updates from Marsh Street to Spring Street, Arncliffe and Spring Street to Bay Street, Banksia.
Tunnelling also continues from our Rockdale site. Our activities at this site include ongoing excavation of the future tunnel roof and floor, as well as trenching to install drainage services and communication conduits.
To learn more, view our latest update from Bay Street to Bicentennial Park, Rockdale.
11 October 2024
This year has seen a huge amount of construction completed and we thank you for your patience during the disruption. Overall, 90 percent of tunnelling is now complete and major road and utility upgrades will be complete in 2025.
Since the two subsidence events in March this year near West Botany Street, tunnelling has paused from our Bicentennial Park site. Transport and its delivery partner, CGU have been reviewing the design of the tunnel in the impacted areas and planning a new construction program.
As a result, the timeframe for opening the M6 Stage tunnel and implementing all final traffic arrangements on President Avenue will change. We will update the community on timeframes when they become clearer.
27 September 2024
A new landmark has transformed the landscape of Kogarah and Brighton-Le-Sands with the installation of a new pedestrian and cyclist bridge over President Avenue.
Two steel sections of President Avenue bridge were lifted into place between 9pm, Saturday 13 July and 5am, Sunday 14 July. President Avenue was closed between West Botany Street and O'Connell Street during this time to facilitate the installation. The three bridge spans were manufactured using 121 tonnes of steel with the main span weighing 70 tonne.
The new President Avenue bridge will link Bicentennial Park and Scarborough Park, allowing pedestrians and cyclists to seamlessly and safely cross over the busy thoroughfare. President Avenue bridge is a key feature of the five kilometre shared pedestrian and cyclist pathway and will be accessible on the completion of the shared pathway in late 2025.
The shared pathway has been designed to connect the community with revitalised natural landscapes, new green spaces, playgrounds, picnic areas and fields, being constructed as part of the M6 Stage 1’s Urban and Design Landscape Plan.
Learn more about the parkland and landscape design plans.
Read an overview of our ongoing construction activities for the shared pedestrian and cyclist pathway in Scarborough Park between Civic Avenue and Chuter Avenue for October 2024.
10 September 2024
A major milestone has been reached on the M6 Stage 1 project with the completion of the final cable pull for the Permanent Power Supply (PPS) on Thursday, 5 September. The last cable was successfully installed between Joint Bay 8 at Kimpton Street and Joint Bay 9 at York Street, Rockdale.
This 7-kilometre underground PPS, stretching from Ausgrid’s Canterbury Substation in Earlwood to the Motorway Operations Centre in Rockdale, will provide reliable power for essential tunnel systems, including lighting and ventilation. This achievement not only concludes a critical phase of the project but also ensures the necessary power supply needed for the M6 Stage 1 tunnels.
The roads previously excavated for the installation of the power supply will be permanently restored. The activities include backfilling of joint bays, restoration of roads, traffic islands and kerbs, and line marking. Road restoration started in June 2024 and is now in its final stages and is steadily advancing along the alignment.
While most of the work will take place during the day, certain sections will be done at night to minimise traffic disruptions.
Due to some delays in authority approvals, we now anticipate the Permanent Power Supply works to be fully completed by Q1 2025.
For more information about the program of works, including an interactive map, please visit our dedicated Permanent Power Supply page.
30 July 2024
Are you familiar with the variety of local businesses at your doorstep?
We encourage the community to shop locally and support small businesses with our handy directory for you to explore. Discover the many great local businesses along President Avenue and West Botany Street.
Help play a role in contributing to your community by making a conscious effort to shop locally year round.
29 July 2024
Our latest Community Update celebrates a major milestone achieved on M6 Stage 1 and provides construction updates on our tunnel portal, tunnelling progress, Princes Highway and President Avenue roadworks, and road restoration on the permanent power supply route.
We also feature the resident site visit from earlier this year which offered a glimpse into the construction that has been happening behind the hoarding. Read on to find out how you can join our next one.
15 April 2024
In a major milestone for the M6 Stage 1, our Urban Design and Landscape Plan (UDLP) has now been partially approved, paving the way for the project to deliver new parks and recreation spaces for the Bayside community.
The approval covers reinstatement of Rockdale Bicentennial Park, the tunnel entrance at President Avenue, and the shared pedestrian and cyclist pathway from Bestic Street to Chuter Avenue.
See an overview of the UDLP approval and the key features being built for the community to enjoy or learn more about the UDLP.
8 March 2024
To celebrate Women in Construction Week and International Women’s Day, Transport for NSW teamed up with the National Association of Women in Construction (NAWIC NSW) to find out what the construction industry can do to continue creating an environment for women to thrive.
NAWIC visited M6 Stage 1 and spoke with our team about what the sector can do to not only attract women but retain and support them throughout their careers.
View the Women in Construction video.
8 May 2023
The M6 Stage 1 demonstrates how industry partnership can build capacity in Aboriginal businesses, supporting the development of employment, skills and commercial sustainability. In this video we hear about the alliance between the Wumara Group and Veris to provide surveying services on the M6 Stage 1 project.
View our video to learn more.
6 February 2023
Transport for NSW’s M6 Stage 1 is proud to play a role in raising the profile of our emerging female talent and the broad opportunities for women to have meaningful careers in construction.
Hear from Project Director, Teresa Avila, alongside some of the Project’s female Engineers and Site Managers who are leading and delivering this mega project.
View the Women in Construction video.
Learn more about the M6 Stage 1 and how this project will change how we travel across Sydney and improve local amenities
Download project factsheets, community updates and notifications
Explore work activities currently scheduled near you
Sign up to receive relevant notifications, construction updates and information right to your email.
Thank you for subscribing to our construction updates. From now on you’ll receive email updates relevant to your area.
Thank you for subscribing to our construction updates. From now on you’ll receive email updates relevant to your area.