President Avenue traffic and access change
Following your feedback to the EIS, changes have been made to traffic and access around President Avenue to improve traffic flow with less stopping and starting.
President Avenue traffic and access change
Following your feedback to the EIS, changes have been made to traffic and access around President Avenue to improve traffic flow with less stopping and starting. They are:
- Moorefield Avenue remaining open as a left in, left out intersection
- Installing traffic lights at Lachal Avenue to provide a right hand turn from President Avenue
- Maintaining the existing parking spaces on Lachal Avenue
- Installing traffic lights and removing a small amount of parking at Civic Avenue to improve access and safety
- Switching traffic directions in Traynor Avenue and Lachal Avenue
- Installing an additional left hand turn lane at the intersection on West Botany Street

Arncliffe Motorways Operations Complex
The Arncliffe Motorways Operations Complex has been constructed as part of the M8 project. A substation, water treatment facility and mechanical fit out of the ventilation facility will be used as part of the M6 Stage 1 project.
Underground connection with M8 Motorway
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Arncliffe ventilation facility
The ventilation outlet was constructed as part of the M8 motorway project and will be use as part of the M6 Stage 1. Elevated ventilation outlets are very effective at ejecting tunnel air high into the atmosphere through a combination of buoyancy and speed.
Once in the atmosphere, the ejected tunnel air dilutes rapidly as it mixes with the surrounding air and becomes indistinguishable from background levels.
Air quality will be continuously monitored at the ventilation outlet to control the ventilation system. This ensures the strict limits outlined in the approval conditions are complied with at all times. Once operating, air quality monitoring data will be publicly available on the new motorway website.
M8 up to four lanes each way
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Building the tunnels
The M6 tunnels are excavated using roadheader machines and a combination of drilling and blasting methods to help reduce the duration of the excavation process.

Southbound tunnel
Placeholder – TBC The tunnels will be built for three lanes but initially marked for two.

Northbound tunnel
Placeholder – TBC The tunnels will be built for three lanes but initially marked for two.

Cut and cover tunnels
As the tunnels pass under Rockdale Bicentennial Park they will rise from 25 metres deep to 10 metres under the surface. This section will be constructed as a ‘cut and cover’ structure, meaning that a deep trench will be dug for the tunnels, which will be completely covered when construction is finished. The land will be returned to parkland and open space for community use

Entry and exit ramps
The twin tunnels will include entry and exit ramps on President Avenue.
Tunnel portals
The areas around the tunnel portal entry and exit ramps will be planted with vegetation to reflect nearby wetlands.
Operational water quality basin
Treats runoff from the tunnel portal and water sensitive urban design discharges it into existing waterways.

O'Neill Street cul-de-sac
New cul-de-sac at O’Neill Street.
Signalised intersection
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Shared cycle and pedestrian bridge
A new shared cycle and pedestrian bridge over President Avenue.

Shared cycle and pedestrian bridge
The new shared cycle and pedestrian bridge over President Avenue provides direct access between to Scarborough Park North and Bicentennial Park.

Shared cycle and pedestrian pathway
New shared cycle and pedestrian pathways connecting Bestic Street, Brighton-Le-Sands to Civic Avenue, Kogarah through the reinstated Rockdale Bicentennial Park. This supports healthier communities and provides safe and direct routes to local centres, schools and other destinations.

Shared cycle and pedestrian pathways
Shared cycle and pedestrian pathways from Bestic Street, Brighton-Le-Sands south to Civic Avenue, Kogarah through the reinstated Rockdale Bicentennial Park. This supports healthier communities and provides safe and direct routes to local centres, schools and other destinations.

Rockdale Motorways Operations Complex (north)
The Motorway Operations Centre will operate 24 hours a day, seven days a week to monitor and operate the tunnel.

Rockdale Motorways Operations Complex (south)
This Motorways Operations Complex consists of the West Botany Street Ventilation facility, substations and power supply for the tunnels, car parking and a disaster recovery site.

Ventilation facility
The southern West Botany Street ventilation outlet will be constructed in the industrial zone on West Botany Street, and the design will take into account its surrounding environment.

Ventilation facility
Elevated ventilation outlets are very effective at ejecting tunnel air high into the atmosphere through a combination of buoyancy and speed.
Once in the atmosphere, the ejected tunnel air dilutes hundreds of times as it mixes with the surrounding air and becomes indistinguishable from background levels.
Air quality will be continuously monitored at the ventilation outlet to control the ventilation system. This ensures the strict limits outlined in the approval conditions are complied with at all times.
Once operating, air quality monitoring data will be publicly available on the new motorway website.

Breakdown bay
Placeholder – TBC Breakdown bays allow for safer pullovers and maintenance operations.

Using the tunnels
The tunnels will be built for three lanes but initially marked for two. They will include:
- A wide cross passage that allows emergency and maintenance vehicles to change directions in the tunnel
- Breakdown bays allow for safer pullovers and maintenance operations
- A tunnel stub for a future connection south
Tunnel stubs
Placeholder – TBC Mainline tunnel stubs to connect to future stages of the F6 Extension.
Cross passage
Placeholder – TBC Cross passages allow for emergency and maintenance access between tunnels.
Shared cycle and pedestrian bridge
Drag the slider from the left to right to compare the existing corridor reserve to the designed road layout.
A new shared cycle and pedestrian bridge will be built over President Avenue.
Princes Highway intersection upgrade
Drag the slider from the left to right to compare the existing corridor reserve to the designed road layout.
Involves the widening of President Avenue and Princes Highway to provide additional turning lanes to increase capacity and improve traffic flow.
Before/after from aerial view
Drag the slider from the left to right to compare the existing corridor reserve to the designed road layout.
New signalised intersection at President Avenue to enter and exit the tunnels. Rockdale Bicentennial Park will be reinstated once the project is complete. The design of the reinstated park with be refined in consultation with Bayside Council, stakeholders and the community.
President Avenue and tunnel portal intersection
Drag the slider from the left to right to compare the existing corridor reserve to the designed road layout.
The new signalised intersection on President Avenue provides access in and out of the tunnels – providing direct connections to the Sydney motorway network.
Before/After: Ador Park
See moreDrag the slider from the left to right to compare the existing Ador Park layout to the new Ador Park layout.
Before/After: Bicentennial Park East
Read moreDrag the slider from the left to right to compare the existing Bicentennial Park East layout to the proposed Bicentennial Park East layout.


Before/After: Bicentennial Park East
Drag the slider from the left to right to compare the existing Bicentennial Park East layout to the proposed Bicentennial Park East layout.
Before/After: Brighton Memorial Playing Fields
See moreDrag the slider from the left to right to compare the existing Brighton Memorial Playing Fields layout to the proposed Brighton Memorial Playing Fields layout.


Before/After: Brighton Memorial Park
Drag the slider from the left to right to compare the existing Brighton Memorial Park layout to the proposed Brighton Memorial Park layout.
Three through lanes (southbound)
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Dedicated signalised left turn lane
Upgrade from three lanes southbound on Princes Highway with a shared straight/ left turn lane to four lanes to provide a dedicated, signalised, left turn from Princes Highway southbound onto President Avenue eastbound. This new left turn lane would be around 70 metres long.

Three lane signalised right turn
Upgrade from a two lane to a three lane signalised right turn northbound from Princes Highway to President Avenue. It will be around 110 metres long and provide additional intersection capacity.
Two through lanes (northbound)
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.
Access retained
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.
Arncliffe construction site – key activities
- Construction of an acoustic shed
- Tunnel excavation and other tunnelling work
- Stockpiling of spoil and spoil haulage
- Construction of an access point (decline) leading into the tunnels
- Construction of a substation and water treatment facility
- Fit-out of a ventilation facility being constructed as part of the M8 motorway project
Construction hours
Monday to Friday 7am to 6pm
Saturdays 8am to 1pm
Tunnelling and spoil management will be carried out at this site 24 hours a day, seven days a week.
Spoil will be stored on site and removed during standard construction hours. Where we may need to remove spoil or take delivery of material that cannot be transported during standard construction hours, the community will be notified in advance.
Indicative construction program
Work will occur on this site for around four years.
Arncliffe construction site – vehicle access
Site is currently being used for the M8 motorway construction. Construction vehicles workers for the project will enter and exit the Arncliffe construction site directly from Marsh Street using the existing signalised intersection (left-in and right-in, left-out only).
Rockdale construction site – key activities
- Construction of an acoustic shed
- Tunnel excavation and other tunnelling work
- Stockpiling of spoil and spoil haulage
- Construction of an access point (decline) leading into the tunnels
- Construction the Operational Motorway Control Centre
Construction hours
Monday to Friday 7am to 6pm
Saturdays 8am to 1pm
Tunnelling and spoil management will be carried out at this site 24 hours a day, seven days a week.
Spoil will be stored on site and removed during standard construction hours. Where we may need to remove spoil or take delivery of material that cannot be transported during standard construction hours, the community will be notified in advance.
Indicative construction program
Work will occur on this site for around four years.
RMS Depot construction site – vehicle access via West Botany Street
Construction vehicles workers will enter and exit the Rockdale construction site directly from West Botany Street. Temporary traffic signals will be installed to manage traffic flow so vehicles can enter and exit the site in all directions.
President Avenue construction site – key activities
- Demolition of buildings and vegetation clearing and removal
- Relocation of utilities
- Temporary stockpiling of spoil and fill materials
- Management of any contaminated land, including acid sulphate soils
- Construction of cut-and-cover structures for entry and exit ramps and the portal
- Construction of the Rockdale Motorways Operations Complex (south) and the Rockdale ventilation facility and substation
- President Avenue intersection upgrade works
- Construction of shared pedestrian and cyclist path and overpass
Construction hours
Construction at this site will be limited to standard construction hours, where feasible and reasonable:
Monday to Friday 7am to 6pm
Saturdays 8am to 1pm
Some work on may need to be carried out at night. The community will be notified in advance if this is required.
Indicative construction program
Work will occur on this site for around three years.
President Avenue construction site – vehicle access via West Botany Street
Construction vehicles can enter and exit the President Avenue construction site from President Avenue (left in/left out only).
Bicentennial Park construction site – vehicle access via President Avenue
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.
Shared pedestrian and cycle pathways construction site at West Botany Street – key activities
- Site establishment
- Vegetation clearing and removal, topsoil stripping areas and preparing the land for the construction of the pathways.
- Excavation of spoil and offsite removal
- Installation of utilities for lighting
- Concreting of the new pathways
- Installation of lighting, line marking and signage
Construction hours
Monday to Friday 7am to 6pm
Saturdays 8am to 1pm
Indicative construction program
Work will occur on this site for around two years.
Shared pedestrian and cycle pathways construction site at West Botany – key activities
- Site establishment
- Vegetation clearing and removal, topsoil stripping areas and preparing the land for the construction of the pathways.
- Excavation of spoil and offsite removal
- Installation of utilities for lighting
- Concreting of the new pathways
- Installation of lighting, line marking and signage
Construction hours
Monday to Friday 7am to 6pm
Saturdays 8am to 1pm
Indicative construction program
Work will occur on this site for around two years.
Princes Highway construction site (7-Eleven service station) – key activities
- Removal of the current buildings including the petrol storage tanks and the rehabilitation of the site
- Relocation of current utilities, stormwater infrastructure and the substation
- Laydown of materials and equipment and parking of construction vehicles
- Road upgrade work along the Princes Highway and President Avenue
- Rehabilitation and landscaping work.
Construction hours
Monday to Friday 7am to 6pm
Saturdays 8am to 1pm
Some work will need to be carried out at night. The community will be notified in advance.
Indicative construction program
Work will occur on this site for around three years.
Arncliffe haulage routes in/out
Truck movements and haulage routes will be restricted to main roads, including access to and from construction sites, to avoid local or residential street and for the safety of pedestrians and road users.
RMS Depot/Bicentennial Park haulage routes in/out
Truck movements and haulage routes will be restricted to main roads, including access to and from construction sites, to avoid local or residential street and for the safety of pedestrians and road users.
Bicentennial Park haulage route in
Truck movements and haulage routes will be restricted to main roads, including access to and from construction sites, to avoid local or residential street and for the safety of pedestrians and road users.
Temporary bus stop changes
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.
Permanent power supply line
New service utilities include a permanent power supply line from Canterbury substation.

Traffic changes: Princes Highway
Includes an upgrade from:
- three lanes southbound with a shared straight/ left turn lane to four lanes to provide a dedicated, signalised, left turn onto President Avenue.
- a two lane to a three lane signalised right turn northbound onto President Avenue.

Traffic changes: TAFE carpark on President Avenue
A new eastbound channelised (separate) right in and right out

Traffic changes: Lachal Avenue
Installing traffic lights at Lachal Avenue to provide a right hand turn from President Avenue and maintaining the existing parking spaces on Lachal Avenue.
Left-in and right-in only (no turn out) on Lachal Avenue due to switching traffic directions in Traynor Avenue and Lachal Avenue.

Traffic changes: Traynor Avenue
Left-out only (no turn in) on Traynor Avenue due to switching traffic directions in Traynor Avenue and Lachal Avenue.

Traffic changes: Cross Street
The project is proposing to remove the westbound right movement onto President Avenue.
Traffic changes: Oakdale Avenue
No changes to access proposed

Traffic changes: Moorefield Avenue
Moorefield Avenue remaining open as a left in, left out intersection.

Traffic changes: West Botany Street
Extended right turning lane from President Ave into West Botany Street.
Installing an additional left hand turn lane at the intersection on West Botany Street.

Traffic changes: Civic Avenue
Installing traffic lights and removing a small amount of parking at Civic Avenue to improve access and safety.

Traffic changes: O'Neill Street
The project is proposing to reconfigure O’Neill Street to a cul-de-sac restricting vehicle access to/from President AvenueExisting.

Traffic changes: O'Connell Street
The project is proposed to extend the right turn lane from President Avenue onto O’Connell Street.
Traffic changes: Crawford Road
No changes to access proposed
Cycle and pedestrian pathways southern extension upgrade
The new shared pedestrian and cyclist pathway has been extended south ending in Chuter Avenue, Monterey.

Traffic volumes: President Avenue, west of M6 Stage 1

Traffic volumes: President Avenue, east of M6 Stage 1

Traffic volumes: Princes Highway, north of Bay Street

Traffic volumes: West Botany Street, north of Bay Street

Traffic volumes: General Holmes Drive, north of Bay Street

Reinstated playground
Recognising the impact on recreational and sporting facilities within Bicentennial Park during construction, we will be providing new and upgraded facilities to compensate for this loss of recreational and open space.
Roads and Maritime is proposing to relocate the existing playground in the Ador Park/McCarthy Park Precinct. The final location will be determined in consultation with local Council and the Stakeholder Liaison Group, as well as input from the local community.
Note: This proposal is not detailed in the EIS and will be subject to separate planning approvals. We will continue to engage with Bayside Council, the Stakeholder Liaison Group and local community to refine this proposal.
Kings Wetland
The tunnel has been located to avoid the Kings Wetland.
Footpath
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.
Brighton-Le-Sands Public School
Placeholder – TBC Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.
Bridge and viewing deck
The bridge will be reinstated with a new viewing deck.

Memorial Playing Fields
The propose upgrade to the Memorial Playing fields during construction will be developed in consultation with all stakeholders including the school, as we understand it is important to maintain the schools current use of this recreation space. The design proposes:
- Construct a new full size synthetic field
- Establish new smaller sized grass fields
- Install new lighting to improve security and extend the usage of the facilities
- Install new drainage to improve water flow
- Provide new amenity block facilities
Note: This proposal is not detailed in the EIS and will be subject to separate planning approvals. We will continue to engage with Bayside Council, the Stakeholder Liaison Group and local community to refine this proposal.
Scarborough Park North
Rockdale Wetland
The Rockdale Wetlands will be revegetated.
Ilinden Sports Centre
The tunnel design and construction impacts avoid the Illinden Sports Centre
Rockdale Bicentennial Park
The reinstatement of Rockdale Bicentennial Park and the East Bicentennial Playing Fields will be finalised through consultation with Bayside Council, community and sporting groups, the Stakeholder Liaison Group and through community feedback.
We are proposing to reinstate the recreational facilities and playing fields with the potential to provide one full size grass field and smaller size grass fields.

Reinstated skate park
Recognising the impact on recreational and sporting facilities within Bicentennial Park during construction, we will be providing new and upgraded facilities to compensate for this loss of recreational and open space.
Roads and Maritime is proposing to relocate the existing skate park in the Ador Park/McCarthy Park Precinct. The final location will be determined in consultation with local Council and the Stakeholder Liaison Group, as well as input from the local community.
Note: This proposal is not detailed in the EIS and will be subject to separate planning approvals. We will continue to engage with Bayside Council, the Stakeholder Liaison Group and local community to refine this proposal.

Consultation
Consultation began in October 2017 with community engagement activities such as doorknocking, the distribution of community updates, pop up events at local shopping centres and briefings with key stakeholders, schools and government agencies. This feedback informed the environmental assessments on increased traffic and congestion, loss of property and green space, local air and water quality as well as noise and emissions from ventilation outlets. From June to August 2018 extensive consultation was carried out to support the release of more detailed project information and design and seek further community feedback.

Consultation
Consultation for the project started in October 2017, following the NSW Government’s announcement to proceed with the M6 Stage 1.
Further consultation with the community and stakeholders was carried out between June and July 2018 when the new project and design information was released.
A Stakeholder Liaison Group was established, which includes Bayside Council and invited representatives from different user groups to meet to discuss construction impacts in the park and reinstatement and future uses once construction is complete. The first meeting was held late October.
Improvement in air quality
Vehicles using tunnels reduces the number of vehicles on surface roads, improving air quality along The Grand Parade and General Holmes Drive by 0.2 to 2 microgram per cubic metre.
Improvement in air quality
Vehicles using tunnels reduces the number of vehicles on surface roads, improving air quality along Marsh Street, Airport Drive and Princes Highway by 0.2 to 2 micrograms per cubic metre.
Increase in emissions
President Avenue and the tunnel portal entry will see a minor increase of 0.2 to 2 micrograms per cubic metre due to more vehicles using this road to enter the tunnel.

No change at ventilation outlets
The emissions from the M6 Stage 1 tunnel will be dispersed high in the air from the ventilation tunnel on West Botany Street. By dispersing high into the atmosphere the result is no change to existing air quality parameters at or around the ventilation outlet site.
No change at ventilation outlets
Under expected traffic conditions for the project, the predicted contribution of tunnel ventilation outlets to local air quality is negligible.
Noise impacts during construction
This is indicative of one construction site however there are multiple construction sites to support the construction of the project.
Construction noise mitigation
Construction noise mitigation measures include:
- Use of acoustic sheds at Arncliffe and Rockdale (north) providing for 24-hour spoil storing.
- Site hoarding at Arncliffe and Rockdale (north).
- Consideration of site layout and equipment selection.
- Advanced community notification of work outside standard construction hours.